News

16-April-2013
Last site update

Enquiries and comments are much appreciated.

Please contact-
mike@hydro-electric-barrel.com

hydroelectric-logo04

15-02- 2013

The project was Stop Go, Stop Go, for many reasons in 2012 but things are on the move again.

More tweaks to the paddle design and a larger prototype 1.9 metre Diameter barrel, plus even the method of manufacture has changed so all components require upgrading to accommodate changes to its size and method of manufacture of the next prototype to be made in 2013.

14-07-12
1/ New 1.5 meter prototype agreed to be tested with two significant modifications and three angle and parameter changes. We believe this will give the required power  output. Engineering drawings close to complete and build and testing to be  underway soon.
2/ Test tank to be constructed in house.
 